Bids

A bid is the price you send for a project to one general contractor or owner. When you price the same job for three general contractors, the project has three bids. Each bid has its own due time, status, decision and result.

MenuEstimator > Projects, then open a project
PermissionManage own projects and bids, or Manage all projects and bids
FeatureEstimator
Can't find it?

What you see depends on your role. If the menu, a button or a setting on this page is missing, ask your administrator to give you the permission listed above or to turn on the feature. Only administrators can turn features on and change site settings.

Add a bid​

  1. Open Estimator > Projects, and open the project.
  2. Click Add bid.
  3. Fill in the form. Only Bid to is necessary while the bid is a draft.
  4. Click Save.

The project page opens, and the bid shows under Bids.

FieldWhat to enter
Bid toThe general contractor or owner the bid goes to.
ContactThe name, email and phone number of your contact there.
Bid typeHard bid, Negotiated, Design assist or Budget.
DueThe date and time the bid is due, in the time zone of the project. The hint under the field shows the time zone.
StatusWhere the bid is. See Bid statuses.
Bid/no-bid checklistYour rating of the points that decide whether to bid. See The bid/no-bid checklist.
Bid decisionNot decided, Bid or Do not bid, and a note about why.
Bid bond requiredSelect it when the bid needs a bid bond.
Prevailing wageSelect it when the job pays prevailing wages.
Our bidThe amount you bid.
Winning bidThe amount of the bid that won, when you know it.
Our rankYour place among the bidders. 1 is the lowest bidder.
NotesOther notes about the bid.

To add a new project and its first bid together, use the New Bid wizard.

The bid/no-bid checklist​

Before you spend days on an estimate, decide whether the job is worth a bid. The Bid/no-bid checklist on the bid form lists ten points. Rate each point from 1 - Unfavorable to 5 - Favorable. A point you do not know yet can stay Not rated.

PointCounts
Relationship with the general contractor or ownerDouble
Fit with the work we do wellDouble
Location and travelOnce
Crew and estimating capacityOnce
Schedule and durationOnce
Number of competing biddersOnce
Payment history and financial strength of the clientDouble
Contract terms and riskOnce
Quality of the drawings and specificationsOnce
Expected marginDouble

Under the points, the checklist shows a score from 0 to 100 and a recommendation. The score changes while you rate. It counts only the points you rated: 100 means every rated point is at 5, and 0 means every rated point is at 1.

ScoreRecommendation
70 or moreBid
45 to 69Review the weak points before you decide
Less than 45Do not bid

You get a recommendation when you rate at least 5 of the 10 points. The checklist only recommends: you make the decision in Bid decision. The bid rows on the project page and in the bid calendar show the score.

Bid statuses​

A bid goes from Draft to In progress to Submitted, and then to Won, Lost or Withdrawn. The Status list shows only the statuses the bid can go to next.

FromThe bid can go to
DraftIn progress, No bid
In progressDraft, Submitted, No bid
SubmittedIn progress, Won, Lost, Withdrawn
Won, Lost or WithdrawnSubmitted
No bidDraft

A bid that is Submitted, Won, Lost or Withdrawn needs its Due date and time and the amount in Our bid. If one of them is missing, the form tells you, and the bid is not saved.

Change or delete a bid​

  • To change a bid, click Edit on its row, on the project page or in the Bid calendar. Change the fields, and click Save.
  • To delete a bid, click Delete on its row, and confirm. You cannot undo it.

When a bid is won​

When a bid is won, set its status to Won, and enter the Winning bid and Our rank if you know them. The bid leaves the bid calendar. The project status does not change by itself: edit the project and set its status, for example to Won.